News Flash

Home Page News and Announcements

Posted on: September 16, 2020

Lake Avenue Revitalization Construction Update

Lake Avenue Update

The Lake Avenue Revitalization Project is nearing completion of the road work, six to seven months ahead of schedule. The final piece of the sewer line and water main, which shoots underneath the railroad tracks, has been tested and completed. Due to the road work moving so far ahead of schedule, an adjustment was made to the work calendar to complete the sidewalks, curbs, and roadwork in-front of the St. James Elementary school to limit interference with the start of the school year.

Highway Teams worked diligently to complete the removal of the road bed and have paved a layer of asphalt from the Railroad tracks to Moriches Road. It is important to note that the asphalt and traffic lines north of the railroad are temporary. Upon completion of the remainder of Lake Avenue, the Highway Department will mill the road, which smooths and levels it out, and they will add a final layer of asphalt from Patricks Way to Moriches Road. This is a necessary step, in order to give adequate time for the material under the road to settle, protecting the new sewer line and water main.

The sidewalks, curbs and new drainage have all been installed from 4th Street to Patricks Way and north of the railroad tracks to Moriches Rd. Laser Industries have begun the final stretch of sidewalk demolition and the construction of concrete walkways and curbs along Lake Avenue from 4th to 1st streets. This process should take approximately 4 weeks to complete.

Highway teams are beginning demolition of the road bed at Woodlawn, going block by block to Railroad Avenue. Each block is expected to take 3-4 business days to complete. All road construction and detours are expected to be wrapped up in mid Fall.

The last and final phase is the streetscape, led by H2M and Traffic Safety director Mitch Crowley. Victorian Ornamental street signage will compliment the decorative crosswalks, stamped concrete and brand new ornate street lighting. The streetscape phase also involves the utility companies removing cluttered old poles, and replacing them with new ones. No road closures are expected for this portion of the project.

In an intergovernmental contract with Suffolk County, the Town of Smithtown has approved the purchase of the old Irish Viking lot on Lake Avenue. Planning to construct a park and municipal parking lot is expected to begin upon the County’s approval of the contract this month. The Town of Smithtown will be coordinating with Celebrate St James on the park design, as financial donors in the construction of the park.

Facebook Twitter Email

Other News in Home Page News and Announcements

Parker

Smithtown Pet of the Week

Posted on: October 20, 2020
Dale and Brennan

Smithtown Pets of the Week

Posted on: October 14, 2020
Angel

Smithtown Pet of the Week

Posted on: October 6, 2020
Road Detour Routes

Lake Avenue Construction Update

Posted on: October 1, 2020
BSC

Drinking and Boating Awareness Campaign

Posted on: September 30, 2020
Shred

Smithtown Holds Largest Shred Event to Date

Posted on: September 30, 2020
Kittens

Smithtown Pets of the Week

Posted on: September 29, 2020
Complete the 2020 Census

Complete the 2020 Census

Posted on: September 28, 2020
Kings Park Lamps

Outdoor Dining Heats Up

Posted on: September 22, 2020
Tyson

Smithtown Pet of the Week

Posted on: September 22, 2020
Mia

Smithtown Pet of the Week

Posted on: September 15, 2020
Ducky

Smithtown Pet of the Week

Posted on: September 8, 2020
Kobe

Smithtown Pet of the Week

Posted on: September 2, 2020
Bailey

Smithtown Pet of the Week

Posted on: August 25, 2020
Water Rescue

Life Saving Rescue A Mile Out to Sea

Posted on: August 19, 2020
Cali, Rocky, and Suzie

Smithtown Pets of the Week

Posted on: August 18, 2020
Cookie

Smithtown Pet of the Week

Posted on: August 12, 2020
From left: Primrose, Bugsy, Amber, Sapphire

Smithtown Pets of the Week

Posted on: August 4, 2020
SupReport_V14

Supervisors Report

Posted on: July 29, 2020
Morty

Smithtown Pet of the Week

Posted on: July 28, 2020
Huck

Smithtown Pet of the Week

Posted on: July 22, 2020
Hazardous Waste Collection

431 Homes Dispose of Hazardous Waste

Posted on: July 22, 2020
Uno

Smithtown Pet of the Week

Posted on: July 15, 2020
Hailee Hurtado

Community Honors Young Hero

Posted on: July 10, 2020
Bay Constable

July 4th Weekend Water Rescue

Posted on: July 9, 2020
Jade

Smithtown Pet of the Week

Posted on: July 7, 2020
OudoorDining

Temporary Outdoor Dining

Posted on: June 3, 2020